N E Oakville H S – Upcoming Finishing Touches: Our Construction Journey

Flooring Contractor scheduled for Monday?? Our site is rather quiet today as we eagerly await the arrival of our finishing trades. The masonry work is nearing completion with the brick

N E Oakville H S – Resolving Construction Delays: Key Steps for Timely Project Completion

The current project has reached a standstill due to trades suspected of prioritizing work at other schools ahead of the impending September closure. Our team urgently requires trades on-site, as

N E Oakville HS – Rooftop Units Installed: Construction Project Update

The construction project has reached significant milestones, as all rooftop units are now installed, achieving a 100% watertight status. The gym floor is equipped with acoustic flooring, anticipating the upcoming

Milton 11 CES – Construction Progress Update: Foundation Footings Begin

Our friends at D’Orazio are making great strides in the northwest corner, enabling us to advance our footing work. This week, we are commencing the footings on the front half

N E Oakville High School – Challenges in Project Timeline: Flooring Delay Impact

Great news! The remaining rooftop units have arrived, and the crane is now onsite, ready for action. Once we successfully install these units, we will be able to pour the

Milton 11 CES -Foundation Progress Update: Key Milestones Achieved

Project Update: Foundation Progress Our foundation walls are now well underway, marking a significant step forward in our construction timeline. Following the completion of the foundation walls, our mechanical and