St. Mark CES – ceiling update

To all trades: we have re-scheduled the remaining installation of T-bar ceiling until next Wed Aug 22nd starting at 7am. We have one week to complete all above ceiling work as well as the sealing of openings. Fire verification is scheduled for the following Monday Aug 27th. All ceilings must be in place. Again, we are closing ceilings next Wednesday. “We’re coming through”🚂🚂🚂🚂

Work on the addition is progressing well. We are scheduled for precast (2nd floor) mid September followed by the roof mid Oct. Our intent is the placement of brick veneer (exterior) prior to Dec 1st.

Still plenty of garbage needs to be picked up

Wooden Fence needed around transformer.

Waiting for an owner

https://larryarbuckle.com

St. Mark Catholic Elem School- Remembering Dave Robichaud

 

I am of the belief that every construction project has a story. The renovation at St. Mark Catholic Elementary School is no different. From the first day /of any project / people meet people for the first time.

This is  where I met Dave. From the “get go” we all knew Dave was a team player with a great sense of humour. Dave led the demolition crew allowing the rest of us to do our jobs. Give Dave a challenge and he conquered all.

The last time I saw Dave was on a Thursday nite cutting a hole in mechanical roof allowing the installation of a roof top unit. He yelled down at me and said “ we’re giv n er”. Sadly, Dave passed away on that week-end.

This  project will be successful and we all feel Dave should not be forgotten as he was a big part of it.

R.I.P Dave and SYOTOS.

From all of us @ St. Mark CES renovation

God Bless

 

St. Mark CES- placement of ceiling tile

We have scheduled the placement of ceiling tile in ( classrooms, library and admin offices starting next Wed Aug 15th. We are asking all trades to complete their work / above ceilings/ prior to Wed. Also, all consultants please proceed with your inspections.

We have also scheduled the placement of ceiling tile / Hallways/ starting a week later Aug 22. The same applies as above.

Up to date ceiling schedule T-bar

We now have full power. Nitesh to receive the “Atta Boy” award for August👍

We have started pouring SOG – addition

Excavation (cutting) behind portables continues.

https://larryarbuckle.com

St. Mark CES- renovation – power shut off tomorrow!

We have generators onsite to provide temp power. Next 3 weeks will be intense🍺🍺

We are ready re- flooring contractor

We are pouring SOG (addition) tomorrow

All portables have been re-located

Asphalt now placed – natural play area

We are preparing parking lot for asphalt scheduled for next week!

We are now in the home stretch. All T bar ceilings classrooms, library and offices complete prior to next Friday. Aug 20th we start T Bar ceilings – hallways!

Drywall ceilings (change-rooms) complete prior to next Friday?

Stay tuned