Flooring Contractor scheduled for Monday?? Our site is rather quiet today as we eagerly await the arrival of our finishing trades. The masonry work is nearing completion with the brick
Continue readingN E Oakville H S – Upcoming Finishing Touches: Our Construction Journey
The current project has reached a standstill due to trades suspected of prioritizing work at other schools ahead of the impending September closure. Our team urgently requires trades on-site, as
It was exciting to witness our contractor beginning the footings at the front of the building. We are in urgent need of backfilling the existing foundation walls, which is a
Continue readingMilton 11 CES – Progress on Backfilling Foundation Walls
The construction project has reached significant milestones, as all rooftop units are now installed, achieving a 100% watertight status. The gym floor is equipped with acoustic flooring, anticipating the upcoming
Continue readingN E Oakville HS – Rooftop Units Installed: Construction Project Update
Our friends at D’Orazio are making great strides in the northwest corner, enabling us to advance our footing work. This week, we are commencing the footings on the front half
Continue readingMilton 11 CES – Construction Progress Update: Foundation Footings Begin
Great news! The remaining rooftop units have arrived, and the crane is now onsite, ready for action. Once we successfully install these units, we will be able to pour the
Continue readingN E Oakville High School – Challenges in Project Timeline: Flooring Delay Impact
Project Update: Foundation Progress Our foundation walls are now well underway, marking a significant step forward in our construction timeline. Following the completion of the foundation walls, our mechanical and
Continue readingMilton 11 CES -Foundation Progress Update: Key Milestones Achieved
Three weeks progress! THE PUSH IS ON!!