Milton 11 CES – Current Progress on Footings Work


Our footings work is currently in progress and presents some complexities. As of now, the crew reports that we are approximately 50% finished. We are awaiting the grout needed for our foundation walls, which is a critical step before proceeding with backfill operations. Following this, we have the placement of our mechanical and electrical (M&E) underground systems scheduled next. We are focused on completing the footings by the end of August. This timeline is essential for maintaining our overall project schedule and ensuring that all subsequent work can proceed smoothly and efficiently.