St. Nicholas CES- standing room only

Site is very busy today as precast continues being placed! If you stand still on this job you will receive β€œwindburn”

Site Service contractor has dropped off piping and scheduled installation this week!

Masonry contractor now on 2nd floor! Open Web Steel Joist to arrive -end of this month- Roof start mid July. Mechanical equipment arrive the week of June 17th. Housekeeping pads to be in place.

Paving contractor to follow site service contractor with stone- prevent mud!

On Deck- windows

www.larryarbuckle.com
πŸ¦…πŸ¦…πŸ¦…πŸ¦…πŸ¦…

St. Nicholas- standing steel

Steel being erected /in preparation/ of precast arriving Monday

Front of building- masonry contractor building walls!

Precast scheduled for Monday / 2nd lift/ once placed masonry contractor to begin 2nd floor! On Deck: OWSJ end of June!

www.larryarbuckle.com